College Park Georgia
College Park, Georgia
·
Completed March 2025
·
14,000 sq ft
- MRI
- CT
- PET

About the project
A standalone 14,000 sq ft imaging center built from foundation through Certificate of Occupancy.
What we solved
Aggressive 11-month schedule driven by equipment delivery dates for two MRI suites.
- Scope
- Ground up
- Duration
- 46 weeks
- Modalities
- MRI, CT, PET
- Square footage
- 14,000 sq ft
- Completed
- March 2025